03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
05/09/2012
|
Letter of notification to the project filed on September 24, 2009 and approved November 19, 2009, that construction on this project was completed on approximately November 11, 2011 filed by S.M.Humphrys. |
09/23/2010
|
Letter of notification advising construction on this project would begin on or shortly after September 13, 2010 filed on behalf of FirstEnergy Service Company by S. Humphrys. |
11/19/2009
|
Staff investigation report and recommendation filed on behalf of PUCO Staff. |
09/25/2009
|
Letter of notification requirements for Bayshore-Jackman and Bayshore-Lemoyne 138 kV Transmission Line Loops to BP Oil project filed on behalf of American Transmission Systems, Incorporated. |
09/25/2009
|
In the matter of the application of American Transmission Systems, Incorporated for Bayshore-Jackman and Bayshore-Lemoyne 138 kV Transmission Line Loops to BP Oil Project.
|