11/19/2009 | Response to letter of notification, construction on this project was completed on approximately October 1, 2009 filed on behalf of FirstEnergy Service Company by S. Humphrys. | 1 |
07/30/2009 | Staff report filed. | 1 |
06/04/2009 | Letter of notification filed by S. Humphrys on behalf of FirstEnergy Service Co. | 17 |
06/04/2009 | In the matter of the application of Beaver-Brookside 138kV transmission line tap to Lorain-Medina Rural Electric Cooperative's Camden Substation. | 14 |
|