CASE NUMBER: 08-1273-EL-BLN
CASE DESCRIPTION: DUKE ENERGY LINE F5381 138KV ELECTRIC TRANSMISSION LINE TAP TO ROCKIES EXPRESS SUBSTATION
DOCUMENT SIGNED ON: 5/3/2024
DATE OF SERVICE: ________________________________________
08/10/2009 Notice that the Duke Energy line F5381 138kV Electric Transmission Line Tap to Rockies Express Substation was completed and made operational on May 23, 2009 filed by S. Lane.
08/10/2009 Letter of notification stating that the Duke Energy Line F5381 138 kV Electric Transmission Line Tap to Rockies Express Substation was completed and made operational on May 23, 2099 filed by S. Lane on behalf of Duke Energy.
01/09/2009 Staff investigation report and recommendation filed.
12/01/2008 In the matter of the application of Duke Energy Corporation letter of notification for line F5381 138kV Electric Transmission Line Tap to Rockies Express Substation.