10/13/2009
|
Case Action form closing case with an effective date of 10/13/2009. |
10/13/2009
|
Final report determining that the project has been put in service filed on behalf of PUCO Staff, J. Henry. |
12/22/2008
|
Correspondence letter stating that Wheeling & Lake Erie Railway is authorized to proceed with field construction projects filed by Staff G. Martin. |
12/17/2008
|
Notice that W&LE has submitted plans and estimates to the Commission for the Vandemark Rd. project filed by D. Reinsel. |
09/10/2008
|
Service Notice |
09/10/2008
|
Finding and order that the stipulation is adopted and approved; by December 9, 2008, W&LE submit site plans and cost estimates; by December 16, 2008, W&LE file letter with docketing advising submission of plans; W&LE notify staff five days before the date the scheduled work is to begin and make arrangements for inspections to be done; project to be completed on or before September 10, 2010. |
09/03/2008
|
Subsidy stipulation filed on behalf of Public Utilities Commission of Ohio Rail Division, Wheeling & Lake Erie Railway Company, Ohio Rail Development Commission, and Medina County by M. Dietrich, P. Geissman, R. Marvin, and W. Callison. |
08/20/2008
|
In the matter of the authorization of Wheeling and Lake Erie Railway Co. to install active grade crossing warning devices in Medina County, Vandemark Road. |