DIS - Case Record for 08-0736-EL-BLN Skip to main content
      
      
CASE NUMBER: 08-0736-EL-BLN
CASE DESCRIPTION: DUKE ENERGY OHIO
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
10/29/2010 Letter informing that construction has been completed for these projects filed on behalf of Duke Energy Ohio by E. Watts.
01/20/2009 Notice withdrawing the Letter of Notification filed for Line F5689 138 kV Transmission Line Loop to Rockies Express Substation on June 16, 2008 filed on behalf of Duke Energy Corporation by S. Lane.
07/24/2008 Staff investigation report and recommendation filed.
06/16/2008 In the matter of the letter of notification regarding a Duke Energy project for the F5689 138 kV Electric Transmission Line Loop to Rockies Express Substation.