CASE NUMBER: 08-0622-EL-BLN
CASE DESCRIPTION: BIXBY-CORRIDOR 345 KV-SERVICE TO JUG STREET STATION
DOCUMENT SIGNED ON: 11/8/2024
DATE OF SERVICE: ________________________________________
11/18/2009 Notice of construction completion electronically filed by Mr. Matthew J Satterwhite on behalf of Ohio Power Company.
09/30/2008 Notice to the Ohio Power Siting Board that construction on the Bixby-Corridor 345KV Line-Service to Jug St. Stations is scheduled to commence on or about October 13, 2008 filed by S. Nourse on behalf of American Electric Power Service.
06/30/2008 Staff investigation report and recommendations filed by PUCO Staff.
05/22/2008 In the mater of the application of Columbus Southern Power Company for approval of the Bixby-Corridor 345 kV Line Service to Jug Street Station.