09/30/2013
|
Entry ordered, that the case be closed and the certificate of environmental compatibility and public need be withdrawn. |
09/30/2013
|
Service Notice |
07/08/2013
|
Motion to withdraw certificate of Environmental Compatibility and
Public Need and memorandum in support electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
03/23/2010
|
Service Notice |
03/22/2010
|
Opinion and order stating that the stipulation be approved and adopted; the certificate be issued to ATSI for the construction, operation, and maintenance of the project as proposed along the preferred route; the certificate contain the 33 conditions set forth in Section V of this opinion, order and certificate. (OPSB) |
11/25/2009
|
Transcript for hearing held October 27, 2009, American Transmission Systems, Inc. before hearing examiners, R. Hussey and K. Bojko. |
11/24/2009
|
Exhibit continued. (Part 3 of 3) |
11/24/2009
|
Exhibits continued. (Part 2 of 3). |
11/24/2009
|
Exhibits for transcript electronically filed 11/24/2009. (Part 1 of 3) |
11/24/2009
|
Exhibits 1-2, staff exhibit 1 and joint exhibit 1 filed for transcript filed electronically 11/24/2009. |
11/24/2009
|
Transcript for hearing held on 11/09/09 electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Hennebert, Julieanna Mrs. |
11/16/2009
|
Transcript for hearing held on November 2, 2009 before Hearing Examiner; Rebecca Hussey at the Public Utilities Commission of Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Hennebert, Julieanna Mrs. |
11/06/2009
|
Joint stipulation and recommendation, findings of fact, and conclusion of law filed by M. Parke on behalf of American Transmission Systems, Incorporated and J. Jones, PUCO staff. |
10/22/2009
|
Proof of publication for Summit and Portage counties filed by J. Toth on behalf of FirstEnergy Service Company. |
10/09/2009
|
Service Notice |
10/09/2009
|
Letter of notification to show proof that FirstEnergy sent out proof of Notice of Public Hearings to property owners and public officials filed by J. Toth on behalf of FirstEnergy. |
10/08/2009
|
Staff Report electronically filed by Mr. James S. O'Dell on behalf of PUCO |
10/07/2009
|
Proof of publication. (Summit & Portage Counties) |
08/10/2009
|
Service Notice |
08/10/2009
|
Entry ordering that ATSI's motions for protective orders be granted, as discussed in finding (4); that ATSI's application be effective on August 20, 2009, as discussed in finding (6); that hearings in this case be scheduled on October 27, 2009, at 6:00 p.m., in R.B. Chamberlin Middle School Auditorium, 10270 Ravenna Road, Twinsburg, Ohio 44087 and the adjudicatory hearing will commence on November 2, 2009,
at 10:00 a.m., at the offices of the Public Utilities Commission of
Ohio, 180 East Broad Street, Hearing Room 11-F, Columbus,
Ohio 43215-3793. |
08/06/2009
|
Correspondence regarding the Chamberlin-Shalersville Transmission Line Supply Project, Ohio Power Siting Board application fee filed by J. Toth on behalf of FirstEnergy Service Company. |
07/31/2009
|
Second motion and memorandum in support for protective order for the reply to the Staff's first data request filed by M. Parke on behalf of American Transmission Systems, Incorporated. |
07/31/2009
|
Confidential document: Response to Staff's first data request filed by M. Parke on behalf of American Transmission Systems, Inc. (6 pgs.) |
07/14/2009
|
Affidavit of proof of service of certified application on additional public officers filed on behalf of American Transmission Systems, Inc. by J.Toth. |
07/14/2009
|
Certificate of Service filed on behalf of American Transmission Systems by J. Toth. |
06/25/2009
|
Affidavit of proof of service of certified application on public officers filed on behalf of American Transmission Systems Incorporated by J. Toth. |
06/25/2009
|
Affidavit of proof of service of certified application on public officers filed on behalf of American Transmission Systems, Inc. by J.Toth. |
06/08/2009
|
Correspondence to inform that the application filed with OPSB on April 6, 2009, has been found to comply with Chapters 4906-01, et seq., of the Ohio Administrative Code filed on behalf of the OPSB by A. Schriber. |
04/06/2009
|
Confidential document target: Motion for protective order, filed by M. Parke on behalf of American Transmission Systems, Inc. |
04/06/2009
|
Application for Certificate continued. ( Part 3 of 3 ) |
04/06/2009
|
Application for Certificate continued. (Part 2 of 3) |
04/06/2009
|
Application for a certificate of Environmental Compatibility and Public Need for the Chamberlin/Shalersville Transmission Line Project filed by M. Parke on behalf of FirstEnergy Service Company. (Part 1 of 3) |
04/06/2009
|
Motion and memorandum in support for admission pro hac vice of Morgan E. Parke filed by M. Beiting, Esq. on behalf of FirstEnergy Service Company. |
04/06/2009
|
Motion and memorandum in support by American Transmission Systems, Incorporated for protective order for certain information produced to staff filed by M. Parke. |
04/01/2008
|
Service Notice |
04/01/2008
|
Entry granting ATSI's motion. (KWB) |
03/26/2008
|
Letter regarding the waiver request of the transmission line rules on behalf of American Transmission Systems, Inc. dated February 8, 2008, filed by K. Lambeck. |
03/14/2008
|
Proof of publication, filed by R. Schmidt, Jr. on behalf of American Transmission Systems, Inc. (Cuyahoga, Portage, and Summit Counties) |
02/08/2008
|
In the matter of the motion for waiver and memorandum in support of American Transmission Systems Inc. for the Chamberlin/Shalersville Transmission Line Project. |