DIS - Case Record for 07-0925-EL-BNR Skip to main content
      
      
CASE NUMBER: 07-0925-EL-BNR
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS INC / ANGOLA MIDWAY 138KV TRANSMISSION LINE RELOCATION FOR I 475 SALISBURY ROAD/DUSSEL DRIVE INTERCHANGE IMPROVEMENTS
DOCUMENT SIGNED ON: 7/17/2024
DATE OF SERVICE: ________________________________________
11/24/2008 Correspondence letter: in response to the Construction Notice filed on August 18, 2007, and advising the Commission this project was completed on approximately October 10, 2008, filed by J. Toth on behalf of FirstEnergy Service Company.
06/16/2008 Letter stating that Angola-Midway 138 kV Transmission Line Relocation for I-475 Salisbury Road/Dussel Drive Interchange Improvements is expected to begin construction on May 30, 2008 filed by J. Toth on behalf of FirstEnergy Service Company.
09/06/2007 Staff report filed.
08/16/2007 In the matter of the application of American Transmission Systems, Inc. for the Angola-Midway 138 kV Transmission Line relocation for I-475 Salisbury Road/Dussel Drive Interchange Improvements, to replace poles and relocate existing transmission lines.