01/10/2008
|
Letter stating that construction on the Warner 138kV Extension Service to RTI project was completed on or about January 3, 2008, filed by S. Nourse on behalf of AEP. |
01/09/2008
|
Notice stating that construction on Warner 138kV Extension Service to RTI project was completed on or about January 3, 2008, filed S. Nourse on behalf of AEP. (FAX) |
10/15/2007
|
Letter stating that Warner 138kV Extension Service to RTI project will commence on or about October 22, 2007, filed by S. Nourse on behalf of AEP. |
08/28/2007
|
Staff investigation report and recommendation filed. |
08/07/2007
|
Correspondence concerning the presence of any endangered, threatened or rare species filed on behalf of American Electric Power by S. Nourse. |
07/18/2007
|
In the matter of the letter of notification for American Electric Power, regarding the Warner 138kV Extension Service to RTI. |