10/29/2010
|
Letter informing that construction has been completed for these projects filed on behalf of Duke Energy Ohio by E. Watts. |
12/11/2008
|
Memo closing case with an effective date of 12/11/08. |
11/26/2007
|
Service notice. |
11/26/2007
|
Entry of the Ohio Power Siting Board ordering that the certificate of environmental compatibility and public need for 05-361 transmission line project is hereby amended to permit the relocation of the line, as described in this order, subject to the conditions set forth by the staff in its report of October 15, 2007. |
11/08/2007
|
Proof of publication, Hamilton County. |
11/08/2007
|
Proof of publication, Brown County. |
10/16/2007
|
Entry ordering that Duke serve copies of the amendment application and give public notice in accordance with Finding (4). (SF) |
10/16/2007
|
Service Notice |
10/15/2007
|
Staff investigation report and recommendation by PUCO staff. |
07/16/2007
|
In the matter of the amended application of Duke Energy, Hillcrest Eastwood 138k V Electric Transmission Line project. |