04/16/2008
|
Memo closing case with an effective date of 4/16/08. |
03/20/2008
|
Service Notice |
03/20/2008
|
Entry ordering that CSX be granted an extension of time until April 21, 2008, to complete the project. (SF) |
03/19/2008
|
Correspondence concerning proposed Grade Crossing for revision that will extend construction completion date 30 days filed on behalf of CSX Transportation by C. Gullakson. |
03/19/2008
|
Memorandum stating that extension request be granted filed by Staff, G. Martin. |
03/19/2008
|
Correspondence stating that the proposed operating frequency will be modified to a different frequency in order for the crossing system circuits to work properly filed on behalf of CSX Transportation by T. Butler. (FAX) |
03/21/2007
|
Entry ordering CSX to submit site plans and cost estimates for the projects by June 21, 2007; that CSX file a letter by June 28, 2007 stating that the site plans and cost estimates have been submitted; that following approval of site plans and cost estimates CSX proceed with construction of the projects with construction to be completed by March 21, 2008. |
03/21/2007
|
Service Notice |
03/08/2007
|
In the matter of the authorization of CSX Transportation to construct active grade crossing warning devices in Crawford , Franklin, Medina and Union Counties. |