CASE NUMBER: 07-0103-EL-BLN
CASE DESCRIPTION: FIRST ENERGY CORP-DALE-WEST CANTON 138 KV TRANSMISSION LINE NEW STRUCTURE ADJACENT TO DALE SUBSTATION PROJECT
DOCUMENT SIGNED ON: 5/2/2024
DATE OF SERVICE: ________________________________________
05/29/2007 Response letter to the project completion notification of the Dale-West Canton 138kV Transmission Line New Structure Adjacent to the Dale Substation project filed by T. Krauss.
03/12/2007 Staff investigation report and recommendation, filed by OPSB staff.
02/01/2007 In the matter of the application of the installation of the Dale-West Canton 138 k V transmission line new structure adjacent to Dale substation project, notification requirement.