CASE NUMBER: 06-1199-EL-BLN
CASE DESCRIPTION: CITICORP OF NORTH AMERICA, INC./CITIGROUP DATA CENTER PROJECT
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
06/21/2007 Notice that construction on the Grief 138 kV Extension Service to Citigroup Data Center Project was completed on June 20, 2007, filed on behalf of Ohio Power Company, dba American Electric Power ("AEP") by S. Nourse.
05/22/2007 Service Notice
05/21/2007 Entry ordered that the request to transfer the certificate in this case to CSP is granted.
04/12/2007 Jointly request of Citigroup and AEP for Board approval to transfer certificate, and upon approval will transfer the underground transmission line extension to AEP, filed by S. Nourse.
11/15/2006 Notification of the start of construction, tentatively scheduled to start November 21, 2006 filed by R. Cooper on behalf of Citigroup.
11/09/2006 Staff Investigation Report and Recommendation, filed by PUCO-staff-Power Siting Board.
10/03/2006 Motion of Citicorp North America, Inc. for waiver of the 90-day filing requirement and memorandum in support filed by Orla Collier
10/03/2006 In the matter of the application of CitiCorp North America, Inc.of the letter of notification, Greif 138 kV, extension service to Citigroup Data Center Project.