DIS - Case Record for 06-0220-GA-GCR Skip to main content
      
      
CASE NUMBER: 06-0220-GA-GCR
CASE DESCRIPTION: VECTREN ENERGY DELIVERY OF OHIO
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
08/15/2007 Memo closing case with an effective date of 8/15/2007.
08/15/2007 Service Notice
08/15/2007 Entry ordering that these cases be closed of record.
03/16/2007 Motion for intervention and memorandum in support, filed on behalf of Interstate Gas Supply by B. Singh.
01/04/2007 Revised quarterly Gas Cost Recovery (GCR) report; three revised schedules submitted, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt. Disregard the previous versions of the GCR rate calculation schedule, schedule 3, and schedule 4 filed on December 27, 2006.
12/28/2006 Quarterly Gas Cost Recovery (GCR) report details the calculation of the proposed monthly GCR rates for the months of February, March and April 2007, filed on behalf of Vectren Energy Delivery of Ohio by J. Schmidt.
12/15/2006 Report of the EGC filing on behalf of Vectren Energy Delivery of Ohio, Inc. filed by J. Schmidt.
11/17/2006 Monthly adjustment to its Expected Gas Cost ("EGC") for December 2006, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
10/18/2006 Monthly EGC filing on behalf of Vectren Energy Delivery of Ohio filed by J. Schmidt.
09/29/2006 Quarterly Gas Cost Recovery (GCR) Report for the months of November and December 2006 and January 2007, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
09/15/2006 Monthly EGC filing for October 2006 filed by J. Schmidt on behalf of Vectren Energy Delivery of Ohio, Inc.
08/18/2006 Gas cost recovery rate calculation filed by J. Schmidt on behalf of Vectren Energy Delivery of Ohio, Inc.
07/18/2006 Monthly EGC adjustment to the expected gas cost for August 2006, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
06/30/2006 Quarterly Gas Cost Recovery Report for the months of August, September and October 2006, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by C. Campbell.
06/16/2006 Monthly EGC Report for July 2006 filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
05/22/2006 Gas Cost Recovery Report on behalf of Vectren Energy Delivery of Ohio filed by J. Schmidt.
04/14/2006 Monthly Expected Gas Cost for May 2006 filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
03/31/2006 Gas Cost Recovery Report filed on behalf of Vectren Energy Delivery of Ohio by J. Schmidt.
03/17/2006 Monthly EGC monthly adjustment to its Expected Gas Cost for April, 2006, filed on behalf of Vectren Energy Delivery of Ohio, Inc. by J. Schmidt.
02/15/2006 Monthly EGC filing on behalf of Vectren Energy Delivery of Ohio, Inc. filed by C. Campbell.
01/18/2006 Monthly EGC filing for February 2006 filed by C. Campbell on behalf of Vectren Energy Delivery of Ohio.
01/05/2006 In the matter of the regulation of the purchased gas adjustment clauses contained within the rate schedules of Vectren Energy Delivery of Ohio and related matters.