02/27/2007 Letter stating that work on the North Bellville 138kV Loop Project was completed October 28, 2006, filed by S. Nourse on behalf of AEP.
04/11/2006 Letter stating that Ohio Power Company dba American Electric Power provides notice to the Ohio Power Siting Board that work on the North Bellville 138kV Loop Project, as described in the company's application filed January 6, 2006 is scheduled to begin on or about May 2, 2006. AEP will notify the Board when construction on this project has been completed filed by S. Williams.
03/06/2006 Staff Investigation Report and Recommendation, North Bellville 138kV Loop project filed by PUCO staff.
01/26/2006 In the matter of the application of American Electric Power for Letter of Notification for the proposed North Bellville 138kV Loop Project.