06/20/2006 Letter of notification stating that this project was completed on June 9, 2006 filed on behalf of FirstEnergy by T. Krauss.
03/22/2006 Letter notifying commission staff that construction on project is expected to begin during the week of March 13, 2006, only a few days after the approximately March 9, 2006 start of construction date indicated in the Letter of Notification, filed on behalf of FirstEnergy Service Company by T. Krauss.
03/13/2006 Ohio Environmental Protection Agency permit issued to National Lime and Stone Company filed by T. Krauss on behalf of FirstEnergy.
03/01/2006 Letter following correspondence related to ODOT and FAA review permits associated with the OPSB Staff's information filed by T. Krauss on behalf of FirstEnergy.
02/24/2006 Letter to Energy Delivery Technical Services/American Transmission Systems, Inc. notifying them that staff has reviewed and accepted the Storm Water Pollution Prevention Plan and the Contingency Agricultural Restoration Plan, and that construction is authorized for these projects, filed on behalf of the OPSB by K. Lambeck.
01/18/2006 Staff Investigation Report and Recommendation.
12/09/2005 In the matter of the letter of notification of FirstEnergy Service Company, a subsidiary of FirstEnergy Corp., on behalf of American Transmission Systems, Incorporated also a FirstEnergy Corp. for the Crissinger-Tangy 138 kV Transmission Line relocation for National Lime and Stone Project.