DIS - Case Record for 05-0951-RR-FED Skip to main content

Case Record For:

05-0951-RR-FED

File a Public Comment
Case Title: NORFOLK SOUTHERN RAILWAY/INDIANA & OHIO CENTRAL RAILWAY
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 7/27/2005
Date Closed: 5/24/2007
Printable Docket Card Service List
View per page
Date FiledSummaryPages
05/24/2007Memo automatically closing case with a effective date of 5/24/2007.1
02/07/2007Entry ordered that the request for extension of time be granted;3
02/07/2007Service Notice2
01/30/2007Letter requesting a 120 day extension of time to install active warning devices at Loveland Avenue, Clermont County, Second Street, Clermont County and Kemper Road, Hamilton County filed by B. Konrad.1
01/18/2007Memo recommending that the Commission grant the request for extension of time for the completion of its projects filed by Staff.2
01/18/2007Request of Indiana & Ohio Central Railway for a 60 days extension to complete the installation of warning devices at all three crossing locations, Loveland Avenue, Clermont, County, DOT #151 334Y, Second Street, Clermont, County, DOT #151 332K and Kemper Road, Hamilton County, DOT #151 336M filed by B. Konrad.1
08/10/2006Service Notice2
08/09/2006Entry ordered; that IOCR's requests for extension of time to complete the projects be granted.3
07/19/2006 Memo stating the request by the Indiana & Ohio Central Railroad for an extension to time to complete three grade crossing projects is reasonable and should be extended for six months, filed on behalf of the PUCO staff-Railroad Section.3
07/18/2006Request for an extension of six months to complete the installation of warning devices at all three crossing locations, filed on behalf Indiana & Ohio Railway Company by B. Konrad.2
08/10/2005Entry ordering that NS and I&O submit to the Commission and ORDC site plans and cost estimates for the projects by November 10, 2005; that following approval of site plans and cost estimates by ORDC, NS and I&O proceed with construction of the projects, with construction to be completed by August 10, 2006.3
08/10/2005Service Notice2
07/27/2005In the matter of the application of the Norfolk Southern Railway and the Indiana & Ohio Central Railway to construct active grade crossing warning devices in Montgomery, Scioto and Clermont Counties.5