CASE NUMBER: 05-0247-EL-BLN
CASE DESCRIPTION: DELTA-WAUSEON 138KV TRANSMISSION LINE TAP TO LEAR AUTOMOTIVE
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
10/17/2005 Letter in response to letter of notification; that construction was completed and the project placed in-service on October 2, 2005 filed by T. Krauss on behalf of FirstEnergy Service Company.
06/01/2005 Response to Letter of Notification filed on February 23, 2005; construction on project is expected to begin on approximately June 1, 2005, filed on behalf of FirstEnergy Services Company by T. Krauss.
03/30/2005 Drawing T-1080-04-01, Lear Property Plan Original, delivered to J. O'Dell, PUCO staff, filed by T. Krauss on behalf of FirstEnergy Service Company
03/30/2005 Staff investigation report and recommendation.
02/23/2005 In the matter of the letter of notification for the proposed Delta-Wauseon 138 kV transmission line tap to lear automotive.