DIS - Case Record for 05-0218-GA-GCR Skip to main content
      
      
CASE NUMBER: 05-0218-GA-GCR
CASE DESCRIPTION: CINCINNATI GAS & ELECTRIC COMPANY
DOCUMENT SIGNED ON: 5/2/2024
DATE OF SERVICE: ________________________________________
09/01/2006 Gas tariff, PUCO No. 18, Sheet No. 76.37 filed by L. Steinkuhl on behalf of Duke Energy Ohio.
08/30/2006 Opinion and Order, ordered; that OCC's motion to intervene in this proceeding is granted; that the stipulation of the parties be adopted; that the company take all necessary steps to carry out the terms in the stipulation and in this opinion and order.
08/30/2006 Service Notice
07/27/2006 Transcript and exhibits of proceeding before Attorney Examiner Jean Kingery, on July 7, 2006.
07/07/2006 Stipulation and Recommendation filed by P. Colbert (Duke Energy Ohio), T. Lindgren (PUCO), L. Sauer (OCC) and B. Singh (Interstate Gas Supply Co.)
07/06/2006 Transcript of hearing held before Gregory Price, Attorney Examiner on June 20, 2006. (concluded)
06/20/2006 Proof of Publication. (Hamilton County)
06/19/2006 Motion for extension of time and memorandum in support filed by P. Colbert on behalf of The Cincinnati Gas and Electric Company dba Duke Energy Ohio. (original)
06/16/2006 Motion for extension of time and memorandum in support filed by P. Colbert on behalf of The Cincinnati Gas and Electric Company dba Duke Energy Ohio.(FAX)
06/13/2006 Prepared testimony of Steven B. Hines on behalf of The Office of The Ohio Consumers' Counsel filed by L. Sauer.
06/13/2006 Testimony of Kathy L. Hagans on behalf of The Office of The Ohio Consumers' Counsel filed by L. Sauer
04/21/2006 Report on the uniform purchased gas adjustment for the 18 month period ending March 1, 2006, filed by D. Leuehe on behalf of The Cincinnati Gas and Electric Company.
04/21/2006 Report on the management and performance audit of gas purchasing practices and policies filed by J. Mierzwa on behalf of Cincinnati Gas and Electric Company.
01/04/2006 Entry ordered; that Cincinnati Gas & Electric Company is granted a waiver of Rule 4901:1-14-04, O.A.C. for purposes of filing an update to its filed GCR rate what would incorporate the NYMEX futures closing price for January, 2006, that the effect of this revision be reviewed during the financial audit of the Gas Cos Recovery mechanism which covers the effective period of this rates.
01/04/2006 Service Notice
12/30/2005 Application for waiver filed by D. Rottinghaus on behalf of The Cincinnati Gas and Electric Company.
12/30/2005 Revised tariff PUCO No.18 filed by R. Butts Jr. on behalf of The Cincinnati Gas and Electric Company.
12/30/2005 Gas cost recovery rate calculations supplemental monthly report for the month commencing January 2006 filed by R. Butts Jr. on behalf of The Cincinnati Gas and Electric Company.
12/15/2005 Revise PUCO Gas No.18 filed by R. Butts on behalf of The Cincinnati Gas and Electric Company.
12/12/2005 Purchased gas adjustment supplemental monthly report filed by R. Butts Jr. on behalf of The Cincinnati Gas and Electric Company.
12/12/2005 Revised PUCO tariff No.18 filed by R. Butts Jr. on behalf of The Cincinnati Gas and Electric Company.
12/06/2005 Motion to intervene and memorandum in support filed by L. Sauer on behalf of Ohio Consumers' Council.
11/15/2005 Service Notice
11/15/2005 Entry ordered that the motion by IGS for intervention be granted. (JK)
11/10/2005 GCR report filed on behalf of Cincinnati Gas & Electric Company by R. Butts.
11/10/2005 Revised tariff, PUCO No.18, filed on behalf of applicant by R. Butts.
10/27/2005 Reply in support of its motion for intervention of Interstate Gas Supply, Inc. filed by B. Singh.
10/17/2005 Memorandum Contra Interstate Gas Supply, Inc's motion for intervention filed by P. Colbert on behalf of The Cincinnati Gas and Electric Company.
10/12/2005 Entry ordered that management / performance audits of the gas purchasing practices and policies of the companies be conducted in accordance with the provisions of RFP No. U04/05-GCR-1 and the findings of this Entry; that each Company enter into a contract with its designated auditor to perform the work required to conduct the management / performance audits pursuant to RFP No. 04/05-GCR-1 and the findings of this Entry, ordered that the cost of the audits be paid by the Companies pursuant to the findings of this Entry.
10/12/2005 Service Notice
10/11/2005 Gas cost recovery report for the month commencing November 2005 filed by R. Butts Jr. on behalf of CG&E.
10/11/2005 Revised tariff sheets, PUCO Gas No. 18, 10.63 and 71.106 to become effective October 28, 2005 filed by R. Butts Jr. on behalf of CG&E.
09/30/2005 Motion for intervention and memorandum in support filed by B. Singh on behalf of Interstate Gas Supply, Inc.
09/14/2005 Entry ordering that public hearings shall be conducted in these matters consistent with the findings herein, each company to cause publication between fifteen and thirty days prior to the date set for the hearings which are as follows; The Cincinnati Gas & Electric Company, June 20, 2006 at 10:00 A.M. ; The East Ohio Gas Company, July 18, 2006 at 10:00 A.M. ; Vectren Energy Delivery of Ohio, October 17, 2006 at 10:00 A.M. and Columbia Gas of Ohio, Inc., November 14, 2006 at 10:00 A.M. all to be held at the offices of the Commission, 180 East Broad Street, Columbus, Ohio 43215.
09/14/2005 Service Notice
09/09/2005 Updated gas tariff to become effective September 29, 2005 PUCO Gas Tariff No. 18 filed on behalf of applicant by R. Butts, Jr.
08/24/2005 Entry ordering that public hearings shall be conducted in these matters consistent with the Findings herein at the time specified in Finding (3); that the audits for Reporting Quarters pursuant to Finding (6), herein, shall be filed with the Commission; that the Commission Staff submit the Request For Proposal for conducting each management/performance audit to various auditing and consulting firms, as required under Chapter 4901:1-14, Ohio Administrative Code, and Findings (8) and (9); that the Companies bear the cost of the management/performance audit as provided in Finding (10); that the notice required in Finding (4) shall be published in substantially that form, as individually applicable, and shall be published in a section of the newspaper other than the legal notice section; that the Companies and the auditors shall observe the requirements set forth herein.
08/24/2005 Service Notice
08/10/2005 Revised tariff, PUCO Gas No. 18 filed by R. Butts, Jr on behalf of CG&E.
07/12/2005 Updated tariff sheets sheet No. 10.60, sheet No. 71.103 filed by R. Butts on behalf of Cinergy.
06/10/2005 Gas cost recovery report for the month beginning July 2005 filed by R. Butts, Jr. on behalf of CG&E.
06/10/2005 Revised tariff pages, PUCO No. 18, filed by R. Butts, Jr. on behalf of CG&E.
05/12/2005 Updated gas tariff to become effective June 1, 2005, filed on behalf of applicant by R. Butts, Jr.
04/12/2005 Updated gas tariff to become effective May 2, 2005 filed by R. Butts, Jr. on behalf of CG&E.
03/11/2005 Revised tariff sheets 10.56 and 71.99 for PUCO Gas Tariff No.18 filed by R. Butts, Jr. on behalf of CG&E.
03/11/2005 Gas Cost Recovery report filed by R. Butts, Jr. on behalf of CG&E.
02/10/2005 Gas Cost Recovery (GCR) Report for the month commencing March 2, 2005, filed on behalf of applicant by R. Butts, Jr.
02/10/2005 Revised tariff sheet numbers and effective date of tariff changes to become effective March 2, 2005, filed on behalf of applicant by R. Butts, Jr.
01/12/2005 In the matter of the regulation of the purchased gas adjustment clauses contained within the rate schedules of Cincinnati Gas & Electric Company and related matters.