04/18/2005
|
Memo stating that grade crossing improvements and/or upgrades ordered have been completed and installed and request that the Docketing Division close cases of record, filed on behalf of PUCO Staff-Railroad Section. |
12/27/2004
|
Service Notice |
12/21/2004
|
Entry stating that NS proceed with the construction of projects, with construction to be completed be December 21, 2005; that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization; that NS notify the commission and ORDC 30 days before the projected date of completion; that at the time staff or ORDC makes its final inspection and if it finds the installations are completed and have been put in service will file a memorandum in this docket directing the docketing division to closed this case of record. |
12/01/2004
|
In the matter of the authorization of Norfolk Southern Railway to upgrade crossings in Putnam and Paulding Counties. |
|