Date Filed | Summary | Pages |
01/15/2008 | Correspondence stating that each of these projects was a transmission upgrade related to the installation of the West Fremont Energy Center, the work on three of these projects was completed and the last of the construction has been completed but the letter of notification was inadvertently omitted filed on behalf of FirstEnergy Service Company by T. Krauss. | 1 |
05/10/2005 | Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss. | 3 |
08/23/2004 | Response to Letter of Notification filed on April 23, 2004, indicating that construction would start July 27, 2004, due to a slight delay project will begin on approximately August 9, 2004, filed on behalf of applicant by T. Krauss. | 1 |
06/11/2004 | Staff investigative report and recommendation filed on by PUCO staff. | 1 |
05/04/2004 | Letter of notification Ottawa Transmission Substation Expansion and Reconfigure Transmission Line Connections, filed on behalf of applicant by T. Krauss. | 2 |
04/23/2004 | In the matter of the letter of notification of American Transmission Systems, Incorporated (Ottawa Transmission Substation) to expand and reconfigure transmission line connection. | 22 |