10/28/2004
|
Final inspection report filed by PUCO staff. |
06/24/2004
|
Field & office report and construction authorization letter to NS for the subject project filed by Railroad Division, PUCO. |
03/04/2004
|
Service Notice |
03/04/2004
|
Entry ordering that the stipulation is approved and that by June 4, 2004 NS submit site plans and cost estimates for the project and by June 11, 2004 file a letter advising that it has been submitted and that the project should be completed by March 4, 2005. |
02/20/2004
|
In the matter of a request for the upgrade of the warning devices at the NS grade crossing at SR 54 (527-984X), Clark County. |
|