DIS - Case Record for 04-0033-RR-UNC Skip to main content

Case Record For:

04-0033-RR-UNC

Case Title: N & S RAILROAD
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: UNC-Unclassified
Date Opened: 1/9/2004
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
12/15/2004The temporary downgrade of the active warning device in Belmont County has been completed filed by PUCO staff.1
11/18/2004Service Notice1
11/18/2004Entry ordering that ODOT's request for an extension of the temporary downgrade be granted in accordance with Finding (4); that ODOT and NS insure that the crossing is flagged in accordance with Finding (4) (SF)2
11/17/2004Memo recommending that the Commission grant ODOT's request for an extension of time filed by G. Martin, PUCO staff.1
11/17/2004Letter requesting that the PUCO revise the completion date for this project to 12/31/04 because of recent flooding in Belmont County filed by J. Barnhouse on behalf of Ohio Department of Transportation.1
09/30/2004Service Notice1
09/30/2004Entry granting ODOT's request for a temporary downgrade until 11/30/04; that ODOT and NS insure that the crossing is flagged in accordance with Finding (4). (SF)2
09/24/2004Letter requesting that the PUCO revise the completion date for project to November 30, 2004 filed on behalf of the Department of Transportation by J. Barnhouse. (FAX)3
09/24/2004Staff recommendation that project completion date be extended until 11/30/04 filed by G. Martin.2
06/30/2004Entry ordered, that ODOT's request for an extension of the temporary downgrade be granted in accordance with Finding (3), that ODOT and NS insure that the crossing is flagged in accordance with Finding (3).2
06/29/2004Service Notice1
06/09/2004Memo recommending that the construction deadline be changed to October 31, 2004, filed on behalf of PUCO Staff by G. Martin-Grade Crossing Planner.2
06/07/2004Request for revision for the completion date for this project filed on behalf of the Department of Transportation by J. Barnhouse.1
04/23/2004Public Notice stating ODOT to temporarily remove railroad warning gates on State Route 148 near Armstrong Mills.1
04/21/2004Entry requesting a temporary downgrade for 120 days and that ODOT and NS insure that the crossing is flagged, also that a copy of this entry be served to the transportation engineer for ODOT District 11; Norfolk Southern;and Belmont County Commissioners.3
04/21/2004Service Notice1
04/09/2004Memo from staff recommending that an entry be issued granting the temporary downgrade of the active warning devise at SR 148 without public hearing, filed on behalf of PUCO staff-Railroad section G. Martin.2
04/08/2004Report of proposed work for project in the plans furnished with Dave Speer on June 26, 2003, filed on behalf of Norfolk Southern Corp. by M. Ciotola.(fax)10
02/25/2004Response to request to temporarily downgrade the active warning device pursuant to our bridge project filed on behalf of applicant by D. Speer.2
01/26/2004Correspondence regarding the recommendation of a flagman used in connection with the proposed rehabilitation of the Captina Creek Bridge filed on behalf of Norfolk Southern Corp. by R. Noe. 2
01/21/2004Letter to Commission opposing the order to stop and flag vehicular traffic to a stop before proceeding across the crossing, but asking that ODOT be required to pay for a flagman at the crossing for the duration of the project, filed on behalf of Norfolk Southern Railway by R. Noe.(FAX)2
01/16/2004Memo stating plans to do rehab work in Belmont County, SR 148 and staff is recommending that the Commission order Norfolk Southern to stop and flag vehicular traffic to stop before proceeding across due to the temporary removal of gates for construction filed by G.Martin.1
01/09/2004In the matter of the application of the Dept. of Transportation requesting a temporary downgrade from signals, flashers and gates to flaggers during the reconstruction of Structure No. BEL-148-1604 over the Captina Creek.6