02/17/2004 | Response to the Construction Notice on project filed on September 23, 2003, advising that construction was completed on February 12, 2004, filed on behalf of FirstEnergy Service Company by T. Krauss. | 1 |
10/17/2003 | Investigation report approving the Construction Notice, filed by J. O'Dell, PUCO staff. | 1 |
09/23/2003 | In the matter of American Transmission Systems, Incorporated construction notice Avon-Emily 138 kV Transmission Line relocation project phase I for the State Route 82 Road Widening Project. | 10 |
|