CASE NUMBER: 03-1485-EL-BNR
CASE DESCRIPTION: CINCINNATI GAS & ELECTRIC COMPANY
DOCUMENT SIGNED ON: 5/1/2024
DATE OF SERVICE: ________________________________________
12/30/2003 Letter advising the Board that the transmission line portion of this project was completed and the line put back in service on 12/13/03 filed by R. McElfresh.
09/03/2003 Letter notifying the Commission that a preconstruction meeting for the subject project has been scheduled for September 4, at 1:30, filed on behalf of applicant by R. McElfresh.
08/22/2003 Additional information filed on behalf of applicant by R. McElfresh.
08/01/2003 Letter to Mr. McElfresh, filed on behalf of PUCO staff by K.Lambeck
07/31/2003 Letter to Mr.O'Dell with revisions to Construction Notice to include Section 7, filed on behalf of Cinergy by R. McElfresh.
07/31/2003 Revised Figure 10, filed on behalf of Cinergy Corp. by R. McElfresh.
07/07/2003 In the matter of the application of Cincinnati Gas & Electric Company for , Miami Fort-Ebenezer Reconductor Project, 138kV Transmission Line Construction Notice.