05/18/2004
|
Letter to Mr. O'Dell stating that the tap for the Watkins Delivery Point was energized on May 29, 2003, filed on behalf of applicant by H. Shamash. |
05/16/2003
|
Correspondence to Dr. Winget relative to the request of 5/12/03, filed on behalf of DP&L by G. Tokar. |
03/18/2003
|
Investigation Report approving the Letter of Notification filed on behalf of PUCO staff by L. Winget. |
03/18/2003
|
Response to Letter of Notification filed on behalf of PUCO Staff by K. Lambeck. |
02/20/2003
|
Letter of Notification and authorization from Buckeye Power to proceed with the project on January 14th, filed on behalf of applicant by H. Shamash. |
02/18/2003
|
In the matter of the Letter of Notification of The Dayton Power & Light Company for the Darby-Delaware 138 kV Line Tap for the Watkins Delivery Point. |