06/13/2003 Letter in response to letter to FirstEnergy on February 19, 2003, project was completed on June 4, 2003, filed by T. Krauss.
03/18/2003 Letter notifying Commission that construction will begin on April 4, 2003, filed on behalf of FirstEnergy Services Co. by T. Krauss.
02/19/2003 Response to Letter of Notification, filed by K. Lambeck, PUCO staff.
02/19/2003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff.
01/03/2003 In the Matter of the Letter of Notification of FirstEnergy Corp., on behalf of American Transmission Systems, Inc, regarding the Pleasant Valley-West Akron West-138kV Transmission Line Tap to Brush Substation, filed by T. Krauss.