12/21/2001
|
Investigation report approving the construction, filed by J. O'Dell, PUCO staff. |
12/21/2001
|
Response letter to Hertzel Shamash filed by K. Lambeck, PUCO staff. |
11/14/2001
|
In the matter of chapter 4906-15-09 of the Power Siting Board rules and regulations, the Dayton Power & Light Co. hereby submits a construction notice to relocate a section of a circuit built at 138 kV design that is operating at 12 kV. |
|