03/20/2003
|
Final report filed on behalf of the PUCO Staff by B. Johrendt. |
01/22/2002
|
Construction authorization letter filed on behalf of the PUCO staff by B. Johrendt. |
08/17/2001
|
Service Notice. |
08/16/2001
|
Entry ordering that the agreement be adopted by the Commission; that W&LE submit to the Commission site plans and cost estimates for the project within 90 days of the date of this entry; that W&LE proceed with construction of the project, to be completed by August 16, 2002. |
07/30/2001
|
In the matter of the request of Wheeling and Lake Erie Railway for the installation of active warning devices at SR 162/Butler Road, (002-016D), Huron County. |
|