Date Filed | Summary | Pages |
10/17/2002 | Memo stating that the grade crossing warning projects involved in these cases have been completed and placed in service; therefore, Staff requests that Docketing Division close the cases of record per Commission order. | 1 |
09/12/2002 | Memo stating that the projects involved in these cases have been completed and placed in service; therefore, staff requests an entry closing these cases of record, filed by G. Martin, PUCO staff. | 1 |
02/28/2002 | Entry ordering Ohio Central Railroad to proceed with construction of project with a completion date of 2/2/02; that Ohio Central Railroad notify the Commission upon completion. | 3 |
02/19/2002 | Memo regarding the Columbus and Ohio River, Ohio Central, and Ohio Southern Railroads construction, filed by G. Martin. | 3 |
08/03/2001 | Service Notice. | 1 |
08/02/2001 | Entry ordering that Columbus and Ohio River Railroad, Ohio Central Railroad, and Ohio Southern Railroad submit to the Commission site plans and cost estimates for the projects within 90 days of the date of this entry; that Columbus and Ohio River Railroad, Ohio Central Railroad, and Ohio Southern Railroad proceed with construction of the project, to be completed by August 2, 2002. | 4 |
07/06/2001 | In the matter of the authorization of the Columbus and Ohio River, Ohio Southern, and Ohio Central Railroad to initiate a joint corridor grade crossing project. | 3 |
|