12/07/2001
|
Service Notice. |
12/06/2001
|
Opinion and order denying Respondent's request for an offset; Respondent should refund $5,497.00 to Complainant |
08/22/2001
|
Reply brief filed on behalf of respondent, Ohio Edison Co., by A. Korkosz. |
08/15/2001
|
Initial brief filed on behalf of respondent, Ohio Edison Co., by A. Korkosz. |
08/13/2001
|
Brief filed on behalf of complainant by P. Hahn. |
07/26/2001
|
Transcript filed for hearing held 7/18/01, (SD), 128 pgs., Submitted. (PUCO-Columbus, OH) |
06/20/2001
|
Service Notice. |
06/19/2001
|
Entry scheduling a hearing at 10:00 a.m. on July 18, 2001, Commission offices. (AE) |
06/11/2001
|
Answer filed by A. Korkosz on behalf of Ohio Edison. |
06/06/2001
|
Service Notice. |
06/05/2001
|
Entry scheduling a settlement conference at 10:00 a.m. on June 19, 2001, 11th Floor, Commission offices. (AE) |
05/21/2001
|
Complaint service letter sent to Ohio Edison, Office of the President. |
05/21/2001
|
In the matter of the complaint for the alleged violation of a line extension agreement. |