10/17/2002
|
Memo stating that the grade crossing warning projects involved in these cases have been completed and placed in service; therefore, Staff requests that Docketing Division close the cases of record per Commission order. |
09/12/2002
|
Memo stating that the projects involved in these cases have been completed and placed in service; therefore, staff requests an entry closing these cases of record, filed by G. Martin, PUCO staff. |
05/25/2001
|
Service Notice. |
05/24/2001
|
Entry ordering that the Railroads submit, within 90 days of this entry, site plans and cost estimates for the crossing upgrades; that the Railroads complete construction of the upgrades by May 4, 2002. |
05/08/2001
|
In the matter of a request for the upgrading of the warning devices under the 2001 Federal Grade Crossing Program. |
|