07/23/2002
|
Entry closing this case of record. |
07/23/2002
|
Service notice. |
06/10/2002
|
Final reports stating upgrades were completed and placed in service; this case can be closed filed by B. Johrendt, PUCO. |
11/19/2001
|
Memo stating that W&LE is now authorized to proceed with the field construction for this project, filed by B. Johrendt, PUCO staff. |
05/09/2001
|
Service Notice. |
05/03/2001
|
Entry ordering that the agreement be adopted by the Commission; that W&LE submit to the Commission site plans and cost estimates for the project within 90 days of the date of this entry; that W&LE proceed with construction of the project to be completed by May 3, 2002. |
04/18/2001
|
In the matter of a request for the modernization of active warning at the highway-railroad grade crossings on CR 98/Easton St. (474-419U) and CR 192/Martindale Rd. (474-4155), Stark County, Wheeling & Lake Erie Railroad. |