Date Filed | Summary | Pages |
10/25/2001 | Service Notice. | 2 |
10/24/2001 | Entry dismissing the complaint and closing this case of record. | 2 |
10/09/2001 | Letter withdrawing the complaint filed on behalf of complainant by K. Caponi. | 1 |
10/01/2001 | Correspondence letter stating that complainant and respondent have been able to come to terms to conclude this proceeding, filed on behalf of complainant by K. Caponi. | 1 |
08/17/2001 | Transcript filed for hearing held August 15, 2001, (SD), 4 pgs., Submitted. (PUCO-Columbus, OH) | 4 |
07/23/2001 | Entry ordering a hearing be held 8/15/01, 1:30 p.m., 11th floor, at the Commission offices. (AE) | 2 |
07/23/2001 | Service Notice | 2 |
06/14/2001 | Entry ordering a settlement conference be held 6/27/01, 2:00 p.m., at the Commission offices. (AE) | 2 |
06/14/2001 | Service Notice. | 2 |
05/04/2001 | Answer and motion to dismiss filed on behalf of respondent, FirstEnergy Corp., by A. Korkosz. | 7 |
05/04/2001 | Answer, motion to dismiss and memorandum in support filed on behalf of respondent, Allegheny Energy Supply Co., by G. Jack. | 9 |
05/03/2001 | Answer and motion to dismiss and memorandum in support filed on behalf of respondent, Allegheny Energy Supply Co., by G. Jack. (Fax copy) | 9 |
04/13/2001 | Complaint service letter sent to the office of the president, FirstEnergy and Allegheny Supply Company | 1 |
04/13/2001 | Complaint service letter sent to H. Peterburg, Office of the President, FirstEnergy and Allegheny Supply Company | 1 |
04/13/2001 | Complaint service letter sent to Gary Jack of FirstEnergy and Allegheny Supply Company | 1 |
04/04/2001 | Complaint letter and copy of complaint mailed to: FirstEnergy and Allegheny Supply Co., office of the president. | 1 |
04/04/2001 | Complaint letter and copy of complaint mailed to: FirstEnergy and Allegheny Supply Co., office of the president. | 1 |
04/03/2001 | In the matter of the complaint of Karen M. Caponi (vs) FirstEnergy Corp. and Allegheny Supply Company relative to the alleged and unfair discontinuance of the electric contract. | 7 |