DIS - Case Record for 01-0026-RR-FED Skip to main content

Case Record For:

01-0026-RR-FED

Case Title: FEDERAL GRADE CROSSING PROGRAM
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 1/5/2001
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
05/09/2002Entry closing this case of record.2
04/18/2002Memo stating that the crossing has been placed in service filed by G. Martin, PUCO.3
04/12/2002Service notice1
04/09/2002Entry ordering that CSX be granted an extension of time until 5/10/02 to complete the project. (AE)2
04/02/2002Memo CSX request for extension of completion date, Suder Ave., Toledo, Lucas County, DOT #867-100B, staff member G. Martin.5
03/29/2002Request for an additional 30-day extension of the due date for the completion of the Suder Avenue crossing project, filed on behalf of CSX Transportation by S. Howard.2
03/08/2002Entry ordering that CSX be granted an extension of time until April 10, 2002, to complete the project. (AE)2
03/07/2002Memo filed by G. Martin, PUCO staff, recommending the extension be granted, with a new deadline of April 10, 2002.4
03/05/2002Request for an additional 30-day extension of the due date for completion of the crossing project, filed on behalf of CSX Transportation by S. Howard.2
02/20/2002Service notice.3
02/19/2002Entry granting NS an extension until 3/18/02. (AE)2
02/13/2002Service notice.3
02/12/2002Memo filed by G. Martin, PUCO staff, recommends that an extension of thirty days be granted.4
02/12/2002Entry ordering that CSX be granted its requested extension. (AE)1
02/07/2002Request for an additional 20-day extension of the due date for completion of the Suder Avenue project, filed on behalf of CSX Transportation by S. Howard.2
01/23/2002Service Notice2
01/16/2002Entry ordering that NS shall complete construction and installation of the project by February 18, 2002. (AE)2
01/16/2002Entry ordering that CSX be granted its requested extension as delineated in Finding 3. (AE)2
01/11/2002Memo filed by G. Martin, PUCO staff, recommending an extension of thirty days to the completion date.5
01/10/2002Memo filed by G. Martin, PUCO staff, recommending that CSX be granted the 30-day extension.4
01/09/2002Letter withdrawing the 60-day extension and requesting a 30-day extension of the due date, filed on behalf of CSX Transportation by S. Howard.2
12/27/2001Memo requesting a 60 day extension of the ordered completion date at the Suder Ave. grade crossing, Lucas County DOT # 867-100B.2
12/27/2001Letter regarding the revised signal force account estimate at the subject location, filed by P. Carine.1
11/14/2001Memo adding two crossings to the case as a matter of record filed on behalf of the PUCO staff by G. Martin.3
10/05/2001Service Notice2
10/05/2001Request that a corrected entry be issued, filed on behalf of the PUCO staff by G. Martin.1
10/04/2001Entry ordering that Norfolk Southern proceed with construction of the project, to be completed by January 18, 2002; that Norfolk Southern notify ORDC and the Commission's railroad section upon completion of each project, at which times the Commission staff will make its final inspections and file a memorandum in this docket directing the Docketing Division to close this case of record.3
09/26/2001Memo requesting the Legal Department of the PUCO to issue an entry to add the 2 additional crossings to the case as a matter of record, filed by G. Martin, PUCO staff.1
01/29/2001Construction authorizations filed on behalf of the Ohio Rail Development Commission.7
01/18/2001Entry ordering that CSX, Indiana & Ohio, Ohio Central, and Norfolk Southern submit to the Commission site plans and cost estimates for the projects within 90 days of the date of this entry; that CSX, Indiana & Ohio, Ohio Central, and Norfolk Southern proceed with construction of the projects, with construction to be completed by January 18, 2002.3
01/05/2001In the matter of a request for the upgrading of the warning devices under 2001 Federal Grade Crossing Program.4
02/15/2000Staff recommendation to grant additional 30 day extension request filed by G. Martin, PUCO.3