CASE NUMBER: 00-1257-EL-ATA
CASE DESCRIPTION: TOLEDO EDISON COMPANY
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
09/06/2002 Letter regarding the Table of Contents and interconnection tariff for The Edison Company P.U.C.O. No. 8, filed by S. Ouellette.
08/22/2002 Finding & Order approving the application; that the EDUs submit the "benchmark" Distributed Generation Report to Market Monitoring staff by September 30, 2002, and submit their annual Distributed Generation Report with the company's 4th Quarter Market Monitoring Report in accordance with Finding 15.
08/22/2002 Service Notice.
03/15/2002 Reply to comments of OCC and comments of the Ohio Partners for Affordable Energy and Ohio Environmental Council, filed on behalf of applicant by A. Korkosz.
03/01/2002 Comments filed on behalf of Ohio Partners for Affordable Energy by D. Rinebolt; Ohio Environmental Council by W. Gruber.
03/01/2002 Comments filed on behalf of OCC by C. Mooney.
02/15/2002 Entry ordering that the movents' motion for an extension of time, is granted. (AE)
02/15/2002 Service notice.
02/08/2002 Joint motion for an extension of time and request for expedited ruling and memorandum in support filed on behalf of OCC by C. Mooney; Ohio Partners for Affordable Energy by D. Rinebolt; and Ohio Environmental Council by W. Gruber.
01/29/2002 Tariff on behalf of The Toledo Edison Company, Ohio Edison Company and The Cleveland Electric Illuminating Company, filed by S. Ouellette.
01/18/2002 Service notice
01/17/2002 Entry ordering that CG&E's motion for extension of time is granted; that the applications for rehearing filed by OPAE/OEC and OCC are denied and that the filing of comments and responses to the interconnection tariffs be filed by February 15, 2002; responses to the comments should be filed by March 1, 2002.
01/04/2002 Memorandum contra the applications for rehearing of OCC, Ohio Partners for Affordable Energy, and The Ohio Environmental Council, filed on behalf of CG&E by P. Colbert.
12/31/2001 Motion for extension of time and memorandum in support filed on behalf of CG&E by P. Colbert.
12/28/2001 Memorandum contra applications for rehearing of the Ohio Consumers' Counsel and Ohio Partners for affordable energy, filed by A. Korkosz.
12/20/2001 Application for rehearing of Ohio Partners for Affordable Energy and Ohio Environmental Council filed by D. Rinebolt.
12/20/2001 Application for rehearing of the Ohio Consumers' Counsel filed by C. Mooney.
11/23/2001 Service Notice.
11/20/2001 Finding & Order approving the stipulation and recommendation and pro forma interconnection tariff and joint exhibits, filed on November 16, 2001; that the EDU's amend their proposed interconnection tariffs filed in the ATA cases.
11/16/2001 Stipulation and recommendation filed on behalf of CG&E by P. Colbert; the PUCO staff by T. McNamee; Ohio Power by M. Resnik; Columbus Southern Power by M. Resnik; Ohio Edison by A. Korkosz; CEI by A. Korkosz; DP&L by A. Vinolus; Monongahela Power by G. Jack; Toledo Edison by A. Korkosz; and Copeland Corp.
07/25/2000 Entry ordering that the first interconnection tariff workshop commence at 10:00 a.m. on August 2, 3000, at the Commission offices. (AE)
07/25/2000 Entry ordering that the first interconnection tariff work- shop commence at 10:00 a.m. on August 2, 2000, at the Com- mission offices. (AE) (2 pgs.)
07/19/2000 Motion to intervene and memorandum in support filed on behalf of Unicom Energy Services by J. Migden.
07/19/2000 Motion to intervene and memorandum in support filed on behalf of Unicom Energy Services by J. Mayer. (6 pgs.)
07/13/2000 Verification page submitted by: J. Burk. (4 pgs.) (Filed 7/12/00)
07/12/2000 Verification page filed on behalf of applicant by J. Burk. (Fax)
07/12/2000 Verification page filed on behalf of applicant by J. Burk.
07/12/2000 Verification page which omitted from the original filing. Filed by: J. Burk. (2 pg.s)
07/10/2000 In the matter of the application of The Toledo Edison Company's interconnection service requirements.