DIS - Case Record for 99-0619-EL-BSB Skip to main content

Case Record For:

99-0619-EL-BSB

Case Title: COLUMBUS SOUTHERN POWER/ORANGE STA
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BSB-Application for a certificate/ substation
Date Opened: 5/18/1999
Date Closed: 12/13/1999
Printable Docket Card Service List
View All
1 - 15 of 37 documents 1 /  3 
Date FiledSummaryPages
02/05/2002Final report for Phase II archeological study, filed on behalf of applicant by J. Schrader.61
03/27/2000Correspondence filed by K. Wissman. 1
03/27/2000Letter regarding Storm Water General Permit for Construction Activity. The staff has reviewed the Storm Water Pollution Prevention Plan submitted on 2/29/2000, for the referenced project. It appears that the portion of the project represented by the plans is consistent with the facility certificated in this case. Consequently, this portion of Condition (8) of Section III of the Certificate has been satisfied, filed by K. Wissman (1 pg) 1
03/27/2000Notice that the Ohio Environmental protection Agency has received the NOI, filed by C. Jone.18
03/27/2000Letter regarding Storm Water General Permit for Construction Activity. The staff has reviewed the Storm Water Pollution Prevention Plan submitted on 2/29/2000, for the referenced project. It appears that the portion of the project represented by the plans is consistent with the facility certificated in this case. Consequently, this portion of Condition (8) of Section III of the Certificate has been satisfied. Filed by K. Wissman (1 pg)1
03/01/2000Response to letter dated January 6, 2000 filed by M. Epstein on behalf o Ohio Historical Society. 1
02/09/2000Notice of American Electric Power receiving a permit, filed by J. Schrader. 2
01/10/2000Correspondence filed by J. Schrader. 5
12/13/1999ICN #0027 Opinion, Order and Certificate ordering that the stipulation filed by Staff and Applicants on November 23, 1999, be approved in its entirety; that a certificate of environmental compatibility and public need for the Orange Station Project be issued for the construction, operation, and maintenance of the facility; that the certificate of environmental compatibility and public need contain the conditions set forth in Section III of this Order. (19 pgs.)19
12/01/1999Transcript filed for hearing held 11/17/99, (SD), 10 pgs., Submitted. (PUCO-Columbus, OH)10
11/30/1999Transcript filed for hearing held 11/16/99, (SD), 12 pgs., Con't. (Olentangy High School, Columbus, OH)12
11/23/1999Joint stipulation and recommended findings of fact and conclusions of law filed on behalf of applicant by C. Schraff; and the PUCO staff by J. Bair and M. Idzkowski. (13 pgs.)13
11/12/1999Proofs of Publication filed on behalf of applicant by J. Schrader. (2 pgs.)2
11/10/1999Correspondence letter to Leslie Warthman filed on behalf of applicant by J. Schrader. (3 pgs.)3
11/01/1999Staff report filed. (37 pgs.)37
 
1 /  3 
      
      
Attorney General:
Bair, Jodi
Attorney Examiner:
Deerwester, Steven