DIS - Case Record for 99-0611-RR-UNC Skip to main content

Case Record For:

99-0611-RR-UNC

Case Title: CSX TRANSPORTATION, INC.
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: UNC-Unclassified
Date Opened: 5/18/1999
Date Closed: 10/17/2002
Printable Docket Card Service List
View All
1 - 15 of 45 documents 1 /  3 
Date FiledSummaryPages
10/17/2002Memo stating that the grade crossing warning projects involved in these cases have been completed and placed in service; therefore, Staff requests that Docketing Division close the cases of record per Commission order.1
09/12/2002Memo stating that the projects involved in these cases have been completed and placed in service; therefore, staff requests an entry closing these cases of record, filed by G. Martin, PUCO staff.1
05/30/2002Entry granting a six-month extension of the construction deadline until October 25, 2002; that, during the month of September, CSX file a status report on this project.2
05/21/2002Memo stating that the railroad staff does not oppose the construction extension request by CSXT, filed by B. Johrendt, PUCO staff.7
05/20/2002Request for an additional six-month extension of the due date for the Schreier Road crossing project or until December 1, 2002, filed on behalf of CSX Transportation by S. Howard.2
04/25/2002Entry ordering that the Boundary Street crossing, Perrysburg, Wood County, DOT No. 155-821J, project is cancelled.2
03/22/2002Service Notice.2
03/21/2002Entry ordering that CSX Transportation submit within 90 days of the date of this entry, project site plans and cost estimates for Commission approval; that CSX Transportation complete construction and installation on the project by August 2, 2002.2
03/15/2002Service Notice.2
03/14/2002Entry ordering that CSX is granted an extension until August 2, 2002; that staff monitor this project in coordination with interconnected projects.2
03/04/2002Memo filed by G. Martin, PUCO staff, reporting the status of this project.2
03/04/2002Memo filed by G. Martin, PUCO staff, stating that ORDC requests that the completion date for this crossing be August 2, 2002.4
02/24/2002Entry ordering that CSX Transportation, Inc. submit within 90 days of the date of the entry, project site plans and cost estimates for Commission approval, that CSX Transportation, Inc complete construction and installation of the project by February 24, 2001.3
02/19/2002Staff request for an entry to delete the W. Boundary St. crossing from this case filed by G. Martin.5
02/14/2002Entry granting CSX's request for an extension until 3/15/02; that staff file a report on the status of this project by 3/5/02. (AE) 2
 
1 /  3 
      
      
Attorney General:
Attorney Examiner: