Date Filed | Summary | Pages |
04/29/1999 | Entry closing this case of record. (1 pg.) | 1 |
04/14/1999 | Final reports filed on behalf of the PUCO staff by B. Johrendt. (11 pgs.) | 11 |
09/04/1998 | Entry ordering that CSX proceed with the installation of roadway gates at Lambert Road (151-869X), Eakin Road (151-842N), Briggs Road (151-843V), Rensch Road (151-856W) and Grove City Road (151-855P) grade crossings; that, pur- suant to the terms of the agreement, the installation be completed with due deligence, but in any event not later than May 31, 1999. (AE) (3 pgs.) | 3 |
08/27/1998 | Field report submitted on behalf of the PUCO staff by B. Johrendt. (35 pgs.) | 35 |
04/09/1998 | Entry ordering that the agreement be adopted by the Com- mission; that the Railroad submit for Commission approval site plans and cost estimates for the projects within 90 days of the date of this entry. (3 pgs.) | 3 |
03/26/1998 | In the matter of a request for the modernization of the active warning devices at Lambert Road (151-869X), Eakin Road (151-842N), Briggs Road (151-843V), Rensch Road (151-854H), and Grove City Road (151-855P) Grove City, Franklin County, CSXT. (10 pgs.) | 10 |
|