Date FiledSummaryPages
09/30/1999Entry closing this case of record. (1 pg.)1
09/30/1999Service Notice2
08/05/1999Memo from B. Johrendt, PUCO staff, stating that notifica- tion of the completion of the Osbourne Road connecting road will be the end of August, 1999, filed.2
08/05/1999Memo from B. Johrendt, PUCO staff, stating that notifica- tion of the completion of the Osbourne Road connecting road will be the end of August, 1999, filed. (2 pgs.)2
05/12/1999Entry ordering that Conrail close the crossings at Osborne Road immediately after construction of the Osborne Road connecting road is completed. (2 pgs.)2
05/12/1999Service Notice3
04/13/1999Memo stating that Conrail has completed the installation of the lights and gates at Jaquay Road, and that ORDC has re- quested that the Osbourne Road grade crossing closure not take place until the construction of the connecting road is completed, filed by B. Johrendt, PUCO staff.2
04/13/1999Memo stating that Conrail has completed the installation of the lights and gates at Jaquay Road, and that ORDC has re- quested that the Osbourne Road grade crossing closure not take place until the construction of the connecting road is completed, filed by B. Johrendt, PUCO staff. (2 pgs.)2
01/05/1999Entry ordering that the completion date of the projects approved herein be extended until February 28, 1999. (AE) (2 pgs.)2
12/23/1998Letter, with attached request for extension of time from Conrail, stating that request is not reasonable and should not be granted, filed by B. Johrendt, PUCO staff.2
12/23/1998Letter, with attached request for extension of time from Conrail, stating that request is not reasonable and should not be granted, filed by B. Johrendt, PUCO staff. (2 pgs.)2
05/01/1998Service Notice3
04/30/1998Entry ordering that the project site plans and costs estimates submitted by Conrail are approved; that Con- rail complete the project installation not later than nine months from the issuance of this entry. (AE) (2 pgs.)2
03/27/1998Memorandum stating that the Legal Division may now generate an entry authorizing construction and incorporate in the authorization on the Conrail Grade Crossing, Lorain County, filed by B. Johrendt, PUCO staff.4
03/27/1998Memorandum stating that the Legal Division may now generate an entry authorizing construction and incorporate in the authorization on the Conrail Grade Crossing, Lorain County, filed by B. Johrendt, PUCO staff. (4 pgs.)4
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Brown,William