Date Filed | Summary | Pages |
01/18/1996 | ICN #0018 Letter stating that the expansion of the River- view Substation was completed on January 5, 1996, and interim rehabilitation will be completed by the end of January, 1996, and permanent rehabilitation of the dis- trubed areas, such as reseeding, will be completed in the Spring of 1996, filed on behalf of applicant by G. Jack. (1 pg.) | 1 |
09/18/1995 | ICN #0017 Copy of permit from the State of Ohio, Department of Transportation concerning highway crossing for the Belmont-Riverview 138 kV line, filed on behalf of applicant by G. Jack. (5 pgs.) | 5 |
08/31/1995 | Letter stating drawings have been approved for the project and construction may begin filed on behalf of PUCO staff by K. Wissman. (1 pg.) | 1 |
08/30/1995 | ICN #0014 Complete set of engineering drawings filed on behalf of applicant by G. Jack. (1 pg.) | 1 |
08/28/1995 | Opinion, Order, and Certificate ordering that the stipulat- ion of findings, conclusions, and recommendation is approved and that a certificate of environmental compatibility and public need is hereby issued for the expansion. (14 pgs.) | 14 |
08/04/1995 | Transcript for hearing held 8/2/95, (SD), 7 pgs., summitted. | 7 |
08/04/1995 | Transcript for hearing held 8/1/95, (Zanesville, Ohio), (SD) 5 pgs., cont. | 5 |
08/02/1995 | ICN #0010 Joint stipulation of findings, conclusions and recommendations filed on behalf of applicant by G. Jack and the OPSB staff by G. Rocco. (7 pgs.) | 7 |
07/19/1995 | ICN #0009 Staff report filed. (24 pgs.) (FILED 7/17/95) | 24 |
07/14/1995 | Letter stating that applicant believes it has satisfied any requirements of the Ohio Historical Society filed by G. Jack. (3 pgs.) (ICN #0008) | 3 |
06/21/1995 | ICN #0007 Proof of publication filed by G. Jack. (4 pgs.) | 0 |
05/26/1995 | Entry scheduling a local public hearing at 7:00 p.m. on 8/1/95 in Marietta, Ohio; scheduling the adjudicatory hearing at 1:30 p.m. on 8/2/95 at the Commission offices. (AE) (3 pgs.) (ICN #0006) | 0 |
05/02/1995 | ICN #0005 Proof of service filed on behalf of applicant by G. Jack. (3 pgs.) | 0 |
04/18/1995 | ICN #0004 Letter to Mr. Gary A. Jack stating that this project has been certified as being complete, filed by the OPSB staff. (2 pgs.) | 0 |
03/17/1995 | ICN #0003 Entry ordering that Mon Power's motion for waiver of the time requirements and for alternate site information is granted. (OPSB) (2 pgs.) | 0 |