DIS - Case Record for 94-1324-RR-FED Skip to main content

Case Record For:

94-1324-RR-FED

File a Public Comment
Case Title: CONRAIL/CSX TRANSPORTATION
Status: AR-Archived
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 8/9/1994
Date Closed: 6/22/1999
Printable Docket Card Service List
View All
1 - 15 of 22 documents 1 /  2 
Date FiledSummaryPages
06/22/1999Entry closing this case of record. (2 pgs.)2
06/11/1999Memo closing this case of record. (1 pg.)1
05/02/1997Entry ordering that the site plans and costs estimates for these projects be approved under the conditions set forth above and that Conrail complete the projects as quickly as possible but in any event not later than February 1, 1998. (AE) (3 pgs.)3
04/28/1997Memo with attached program letters, encumbrance estimates, Form ODOT-lf070770, field reports, and design plants for mentioned crossings, filed on behalf of PUCO railroad section by B. Johrendt.84
04/28/1997Program letters, encumbrance estimates, Form ODOT-LFO7DT7O, field reports (FOC), and design plans for the following projects, filed on behalf of the PUCO staff by B. Johrendt: (83 pgs.) 1. Lucas County, Benore Road, Conrail 2. Lucas County, Oakdale Avenue 3. Lucas County, Phillips Avenue 4. Fulton County, Fulton Street 5. Erie County, Rye Beach Road 6. Lucas County, Sylvania Avenue83
12/20/1996Entry ordering that the site plans and cost estimates for this project be approved under the conditions set forth in Finding 3 and that Conrail complete the project as quickly as possible, but in any event not later than September 20, 1997. (AE) (3 pgs.)3
12/13/1996Memo authorizing Conrail to proceed with the construction of the proposed grade crossing warning system in accordance with the abbreviated plan and the provisions set forth filed by B. Johrendt, PUCO staff. (6 pgs.)6
11/26/1996Service Notice0
11/25/1996Entry ordering that the October 21, 1996 entry in this docket should be corrected as forth in finding (2), and that CSX complete the project as quickly as possible, but in any event not later than October 21, 1997. (AE) (1 pg.)1
11/14/1996Entry ordering that the site plans and cost estimates for this project submitted by Conrail be approved under the conditions set forth in the ORDC memo, to be completed by November 21, 1997. (AE) (2 pgs.)2
11/04/1996Program letter, encumbrance estimate, Form ODOT-LFO7DT7O, field report (FOC), and design plans for the Conrail Grade Crossing, CR 225/Perry Road, Stark County program, filed by B. Johrendt, PUCO staff. (6 pgs.)6
10/25/1996Entry ordering that the site plans and costs estimates for these projects submitted by Conrail be approved under the conditions set forth in the ORDC memo, and it is further ordered that Conrail complete the projects as quickly as possible but in any event not later than October 23, 1997. (AE) (2 pgs.)2
10/21/1996ODOT memo authorizing Conrail to proceed with the construct- ion of the proposed grade crossing warning system in accord- ance with the abbreviated plan and the provisions set forth in this case filed by B. Johrendt, PUCO staff. (6 pgs.)6
10/21/1996Entry ordering that the site plans and costs estimates for this project submitted by Conrail be approved under the conditions set forth in this entry and that Conrail complete the project as quickly as possible but in any event not later than October 21, 1997. (AE) (3 pgs.)3
10/10/1996Program letter, encumbrance estimate, Form ODOT-LFO7DT7O, field report (FOC), and approved Conrail's estimates and abbreviated plans for the CSXT Grade Crossing, Broad Blvd. (142-OO7P), City of Cuyahoga Falls, Summit County, filed by B. Johrendt, PUCO staff. (14 pgs.)14
 
1 /  2 
      
      
Attorney General:
Attorney Examiner:
Veri,Joan