Date Filed | Summary | Pages |
06/10/1994 | ICN #0009 Letter stating that construction of the Feeder 5483 Loop Through Simpson Substation was completed on June 3, 1994, filed on behalf of applicant by W. Chaney. | 0 |
03/08/1994 | ICN #0008 Letter stating that construction of the Feeder 5483 Loop through Simpson Substation is planned to begin on March 15, 1994, filed on behalf of applicant by W. Chaney. | 0 |
12/10/1993 | ICN #0007 Copy of letter to Mr. W. T. Chaney stating that this project does continue to qualify under the rules for the Letter of Notification process, filed by K. Wissman, OPSB staff. | 0 |
12/09/1993 | ICN #0006 Investigation report approving letter of notifi- cation, filed by L. Winget and R. Apanius, PUCO staff. | 0 |
11/02/1993 | ICN #0005 Amendment to the letter of notification filed on behalf of applicant by W. Chaney. | 0 |
10/05/1993 | ICN #0004 Response to Letter of Notification, filed by K. Wissman, OPSB staff. | 0 |
09/24/1993 | ICN #0003 Investigation report approving letter of notifi- cation, filed on behalf of the PUCO staff by L. Winget, R. Apanius, J. O'Dell, and F. Heizer. | 0 |
09/23/1993 | ICN #0002 Letter, with attached letter from the Ohio Historic Preservation Office detailing the findings of the cultural resources investigation of the project area, filed on behalf of applicant by W. Chaney. | 0 |
09/01/1993 | ICN #0001 In the matter of the application of The Cin- cinnati Gas & Electric Company for a board letter of notification for the porposed Feeder 5483 Loop through Simpson Substation. | 0 |