Date Filed | Summary | Pages |
10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
10/19/1992 | ICN #0005 Letter informing the Commission that construction on this project was completed on September 28, 1992, filed on behalf of applicant by M. Ams. | 0 |
08/25/1992 | ICN #0004 Letter stating that the planned date of initial construction on this project is August 19, 1992, filed on behalf of applicant by M. Ams. | 0 |
07/14/1992 | ICN #0003 Response to Letter of Notification filed on behalf of the OPSB staff by J. Kennedy. | 0 |
07/13/1992 | ICN #0002 Investigation report Letter of Notification filed on behalf of the OPSB staff. | 0 |
06/10/1992 | ICN #0001 In the matter of the Letter of Notification covering the installation of a 138kV transmission line to serve the new Issler Distribution Substation, filed on behalf of Cleveland Electric Illuminating Company. | 0 |