Date Filed | Summary | Pages |
10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
09/29/1992 | ICN #0005 Letter informing Commission that construction on this project was completed on September 15, 1992, filed on behalf of applicant by M. Ams. | 0 |
04/16/1992 | ICN #0004 Letter stating that the planned date of initial construction of this project is the week of April 13, 1992, filed on behalf of applicant by M. Ams. | 0 |
04/15/1992 | ICN #0003 Letter in response to letter of notification, filed on behalf of the PUCO staff by J. Kennedy. | 0 |
04/01/1992 | ICN #0002 Investigation report Letter of Notification filed on behalf of OPSB staff. | 0 |
02/21/1992 | ICN #0001 In the matter of the Letter of Notification covering the installation of a single circuit 138kV supply line to the Wentworth Distribution Substation, filed by Toledo Edison Company. | 0 |