Date Filed | Summary | Pages |
10/16/2000 | ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. | 13 |
10/16/2000 |
ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates
| 7 |
10/16/2000 | ICN #0223 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.) | 6 |
12/16/1996 | Letter stating the completed date for the project filed on behalf of applicant by G. L. Cunningham. (1 pg.) | 1 |
06/04/1996 | ICN #0221 Letter to Mr. T. C. Burgess stating that the engineering drawings for this project submitted on May 13, 1996, have been reviewed by the staff, and construction of the portion of the project depicted by the drawing may be started, filed on behalf of the PUCO staff by K. Wissman. (1 pg.) | 1 |
05/30/1996 | ICN #0220 Revised Sheet 6 of Plan and Profile drawing TZ-374-F of the Kirby-Tangy portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
05/21/1996 | ICN #0219 Letter stating that construction for the Crissinger-Roberts portion of the subject project was completed and placed in service on April 8, 1996; construc- tion for the Kirby-Roberts portion was completed and placed in service on May 8, 1996; the Kirby 138-69 kV Substation construction was completed on April 15, 1996; the 138 kV bus equipment and the 138-69 kV transformer at Kirby Sub- station were placed in service on May 8, 1995; the 69 kV portion of Kirby will be energized upon completion of re- maining 69 kV transmission line work, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
04/18/1996 | ICN #0218 Letter to Mr. T. C. Burgess, Ohio Edison, stating that they may proceed with construction of the portion of the project depicted by the drawing submitted on March 22, 1996, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
04/18/1996 | ICN #0217 Revised Sheet 8 of Plan & Profile drawing TZ-374-F of the Kirby-Tangy portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
03/26/1996 | Final archaeological survey report filed on behalf of applicant by T. C. Burgess. (6 pgs.) | 6 |
03/15/1996 | ICN #0215 Letter to Mr. T. C. Burgess, Ohio Edison, stating that Ohio Edison may proceed with construction of the portion of the project depicted by the drawings, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
03/14/1996 | ICN #0214 Revised sheet 7 of Plan and Profile drawing TZ-375-F of the Kirby-Roberts portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
01/26/1996 | ICN #0213 Letter to Mr. T. C. Burgess approving the drawings submitted on January 3, 1996, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
01/25/1996 | ICN #0212 Plan and profile drawings TZ-376-F, Sheets 1 & 2, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
01/04/1996 | Letter stating that the portion of the project depicted by the drawings may proceed with construction filed by K. Wissman, PUCO staff. (1 pg.) | 1 |