Date FiledSummaryPages
10/08/1993Memo closing case with effective date of 10/8/93.0
10/02/1991ICN #0006 Letter stating that the construction was completed September 19, 1991, filed on behalf of applicant by T. Burgess.0
07/09/1990ICN# 0005 Letter filed on behalf of the applicant stating that the construction is scheduled to begin on July 9, 1990 filed by T. C. Burgess.0
06/22/1990ICN #0003 Letter in response to Letter of Notification filed by Ohio Edison Company informing the company that the filing meets the informational requirements for a Letter of Notification and the project may proceed, filed on behalf of OPSB by J. Lehr Kennedy.0
06/22/1990ICN #0004 Memo to OPSB from James Lehrn Kennedy stating that Jim Kennedy recommends that the project qualify for the Letter of Notification process, filed on behalf of the OPSB.0
06/19/1990ICN0002 Letter of Notification filed on behalf of Ohio Edison for the Evergreen-Highland #3 138kV line relocation and line extension to service new WCI Substation.0
06/19/1990ICN# 0001 Request for waiver of ninety-day filing requirement prior to construction of OEC's Evergreen Highland #3 138 kV Line Relocation.0
 