Date Filed | Summary | Pages |
05/28/1992 | ICN #0006 Letter stating that this project was completed on May 17, 1992, filed on behalf of applicant by M. Ams. | 0 |
12/06/1990 | Memo from R. Gooden, PUCO staff, stating that this case is closed. | 0 |
12/12/1989 | ICN# 0005 Letter filed on behalf of the applicant stating that the construction date is the week of December 11, 1989 filed by M. Ams. | 0 |
09/11/1989 | ICN# 0004 Letter filed by M. Apanius for the site visit. | 0 |
09/11/1989 | ICN# 0003 Letter filed on behalf of the OPSB stating that the application qualifies for the LON filed by J. Kennedy. | 0 |
09/11/1989 | ICN #0002 Exhibit-3 filed on behalf of CEI by M. Ams. | 0 |
08/11/1989 | ICN. #0001 Letter of Notification, Davis-Besse Mobile Sub- station Tap, by Toledo Edison Company. | 0 |