Date Filed | Summary | Pages |
10/25/1993 | ICN #006 Letter filed on behalf of applicant that the construction was completed on September 30, 1993 filed by T. C. Burgess. | 0 |
05/12/1992 | ICN #0005 Letter stating that construction of this project is to begin on April 6, 1992, filed on behalf of applicant by T. Burgess. | 0 |
12/06/1990 | Memo from R. Gooden, PUCO staff, stating that this case is closed. | 0 |
07/06/1989 | ICN. #0004 Correspodence letter filed by J. Kennedy on behalf of OPSB. | 0 |
07/06/1989 | ICN. #0003 Correspondence letter filed by M. Apanius/ OPSB. | 0 |
07/06/1989 | ICN. #0002 Correspondence letter filed by J. Kennedy, OPSB. | 0 |
06/16/1989 | ICN. #0001 Letter of Notification of Babb-East Akron 138 kV: Aetna-Babb Portion Addition of New Circuit on Open Circuit Side of Existing Towers. | 0 |