Date Filed | Summary | Pages |
03/13/2024 | Notice of Compliance with Condition 2 - Ohio Historic Preservation Office Assessment Letter electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 3 |
02/23/2024 | Service Notice. | 1 |
02/23/2024 | Staff Report of Investigation electronically filed by Ms. Justine Patmon on behalf of Staff of the OPSB. | 8 |
02/12/2024 | Response to Fourth Set of Data Requests from the Staff of the Ohio Power Siting Board electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 3 |
01/29/2024 | Response to Ohio Power Siting Board Staff's Second and Third Set of Data Requests dated January 10 and 17, 2024 electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 6 |
01/08/2024 | American Transmission Systems, Incorporated’s
Response to Ohio Power Siting Board Staff’s first set of Data Requests dated December 15, 2023 electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 6 |
12/12/2023 | Letter of Notification and Proof of Publication for the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and
Wentworth Substation Expansion Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 6 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part XIII of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 39 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part XII of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 99 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part XI of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 77 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part X of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 145 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part IX of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 27 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part VIII of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 26 |
12/04/2023 | Notification regarding the Angola-Eber-Vulcan 138 kV Transmission Line Rebuild and Wentworth Substation Expansion Project (Part VII of XIII; Exh. 23, Continued) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. | 24 |